Launch week prep — the engineering side
Launch week starts Wednesday. The engineering side of the prep is
straightforward but worth writing down so the team has a single
reference.
Capacity headroom
Every region runs at 4x projected peak load through May 5. The
projected peak comes from the private-beta signup rate scaled by
the most generous launch-bump multiplier we modelled.
Change freeze
A strict change freeze begins Wednesday at 18:00 UTC and lifts on
Monday May 4 at 09:00 UTC. Hotfixes require two on-call leads to
sign off; planned changes are deferred to the post-freeze window.